Gup contracted under the CISG to deliver a computer to Jud on 31 March. On 2 March, Gup informs Jud that due to rising costs, he will not deliver the computer. Under the UN Convention on Contracts for the International Sale of Goods (CISG), which remedy is available to Jud on 2 March?
- 1Jud must accept that performance is impossible and has no legal remedy
- 2Jud may declare the contract avoided and claim damages immediately on 2 March✓
- 3Jud must allow the contract to continue until 31 March and then sue for damages
- 4Jud may avoid the contract, but cannot sue for damages until after 31 March
Correct answer
Jud may declare the contract avoided and claim damages immediately on 2 March
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Business Studies?
Practice full-length Business Studies mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on International Commercial Contracts?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Business Studies · International Commercial Contracts