Computer · Construction Equipment and Techniques
Generally, at what rate should a vertical slip formwork be lifted during continuous concrete construction?
- 11 m per hour
- 25 - 10 cm per hour
- 320 - 30 cm per hour✓
- 450 - 60 cm per hour
Correct answer
20 - 30 cm per hour