Free float in project network analysis is primarily used to:
- 1Identify the activities which can be delayed without affecting the total float of either preceding or succeeding activities
- 2Establish critical paths and strict allocation of crashing priorities
- 3Identify the activities which can be delayed without affecting the earliest start time of succeeding activities✓
- 4Identify the activities which can be delayed without affecting the total float of preceding activities
Correct answer
Identify the activities which can be delayed without affecting the earliest start time of succeeding activities
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Computer?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Construction Management?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Computer · Construction Management