Industrial Engineering · Operations Research and Project Management
For which of the following applications are deterministic models usually NOT implemented?
- 1Maintaining the air conditioner's temperature
- 2Inventory management where demand and supply are known
- 3PERT (Program Evaluation and Review Technique)✓
- 4CPM (Critical Path Method)
Correct answer
PERT (Program Evaluation and Review Technique)
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Industrial Engineering?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Operations Research and Project Management?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Industrial Engineering · Operations Research and Project Management