For the pipe earthing process, which of the following steps is correct to ensure proper installation and long service life?
- 1Burying a cast iron pipe vertically in the ground without any filling
- 2Using only dry soil to fill the pit around the pipe to avoid corrosion
- 3Laying a copper strip horizontally just below the surface of the soil without any treatment
- 4Placing a GI pipe of about 2–3 m length in a pit, surrounded by alternate layers of charcoal and salt, and watering it periodically✓
Correct answer
Placing a GI pipe of about 2–3 m length in a pit, surrounded by alternate layers of charcoal and salt, and watering it periodically
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Physics?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Earthing?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Physics · Earthing