For the construction of Water Bound Macadam (WBM) roads, what is the correct sequence of operations after spreading coarse aggregates?
- 1Dry rolling, wet rolling, application of screening and application of filler
- 2Dry rolling, application of filler, wet rolling and application of screening
- 3Dry rolling, application of screening, wet rolling and application of fi ller
- 4Dry rolling, application of screening, application of filler and wet rol ling✓
Correct answer
Dry rolling, application of screening, application of filler and wet rol ling
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Physics?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Highway Engineering?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Physics · Highway Engineering