Computer · Tunnel Engineering
For initial surveys of tunnels, the following activities are involved: (a) Marking portal points with concrete pillars on the ground. (b) Marking tunnel obligatory points on the topographical maps. (c) Driving lines between the fixed obligatory points. (d) Preliminary setting of the tunnel on the topographical survey of India maps. The correct sequence of these activities is:
- 1(c), (b), (d), (a)
- 2(d), (b), (c), (a)✓
- 3(a), (b), (c), (d)
- 4(b), (a), (d), (c)
Correct answer
(d), (b), (c), (a)
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Computer?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Tunnel Engineering?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Computer · Tunnel Engineering