Computer · Highway Engineering
For construction of Water Bound Macadam (WBM) roads, which of the following is the correct sequence of operations after spreading the crushed aggregates?
- 1Wet rolling, application of binding material, dry rolling, filling voids with screening
- 2Dry rolling, wet rolling, application of binding material, filling voids with screening
- 3Filling voids with screening, application of binding material, dry rolling, wet rolling
- 4Dry rolling, filling voids with screening, wet rolling, application of binding material✓
Correct answer
Dry rolling, filling voids with screening, wet rolling, application of binding material
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Computer?
Practice full-length Computer mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Highway Engineering?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Computer · Highway Engineering