Mathematics · Operation Research
For a project activity, the optimistic time, pessimistic time, and most likely time are 4, 14, and 6 days respectively. Under PERT, its expected average time is:
- 19 days
- 212 days
- 37 days✓
- 410 days
Correct answer
7 days
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Mathematics?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Operation Research?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Mathematics · Operation Research