Mathematics · PERT and CPM
For a PERT network where the critical path has an expected completion time of 22 days and a standard deviation of 5 days, the probability of completing the project in 27 days is:
- 10.977
- 20.964
- 30.919
- 40.841✓
Correct answer
0.841