Computer · Highway Engineering
For a highway project, a preliminary survey is conducted primarily for _______.
- 1topographic details and soil survey✓
- 2quality control tests
- 3design details of embankment
- 4preparation of subgrade
Correct answer
topographic details and soil survey
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Computer?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Highway Engineering?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Computer · Highway Engineering