Computer · Soil Mechanics and Foundation Engineering
For a certain loading condition, a saturated clay layer undergoes 40% consolidation in a period of 178 days. What would be the additional time required for a total of 60% consolidation to occur?
- 189 days
- 2222.5 days✓
- 3329.5 days
- 4400.5 days
Correct answer
222.5 days