Mathematics · Building Estimation
For a brickwork of 10 m3 with 1:6 cement mortar, check the following statements: (A) Volume of cement required is 0.75 m3. (B) Number of bricks required is 5000.
- 1(A)-False, (B)-False
- 2(A)-True, (B)-False
- 3(A)-False, (B)-True✓
- 4(A)-True, (B)-True
Correct answer
(A)-False, (B)-True