Mathematics · Estimation and Costing
For a 2.5 cum thick cement concrete (1 : 2 : 4) damp-proof course, the dry volume quantity of stone chips required will be approximately:
- 12.80 cum
- 22.50 cum
- 32.20 cum✓
- 42.00 cum
Correct answer
2.20 cum