General Studies · Project Management (PERT/CPM)
Examine the following statements: Statement 1: The critical path of PERT represents the shortest path in time in the project network. Statement 2: Activities on the critical path have zero float (slack time). Choose the correct answer from the options given below:
- 1Statement 1 is false, but Statement 2 is true✓
- 2Both Statement 1 and Statement 2 are false
- 3Statement 1 is true, but Statement 2 is false
- 4Both Statement 1 and Statement 2 are true
Correct answer
Statement 1 is false, but Statement 2 is true
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for General Studies?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Project Management (PERT/CPM)?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in General Studies · Project Management (PERT/CPM)