Accounting · IAS 16 Property, Plant and Equipment
Era Construction Plc commenced the construction of a new administrative office building for its own use on 1 January 20X4. The following costs were incurred during the construction period until completion on 30 September 20X4: - Purchase price of land: $5,000,000 - Stamp duty on land purchase: $250,000 - Legal fees for land acquisition: $150,000 - Site preparation and clearance costs: $300,000 - Building materials: $1,200,000 (includes $100,000 for materials damaged during a storm) - Direct labour costs: $800,000 (includes $50,000 for idle time due to breakdowns) - Architect's fees: $100,000 - General administrative overheads allocated based on staff time: $200,000 - Interest on specific construction loan ($2,000,000 at 8% p.a. for 9 months): $120,000 - Investment income earned on temporary investment of surplus loan funds: $10,000 The building was ready for its intended use on 30 September 20X4. What is the total cost that should be capitalised as part of Property, Plant and Equipment (IAS 16) for this building asset?
- 1$7,920,000
- 2$7,760,000✓
- 3$7,940,000
- 4$7,810,000
Correct answer
$7,760,000
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Accounting?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on IAS 16 Property, Plant and Equipment?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Accounting · IAS 16 Property, Plant and Equipment