During transformer testing, the short-circuit test and open-circuit test are typically performed by connecting the instruments on which sides respectively?
- 1Low Voltage (LV) side and High Voltage (HV) side respectively
- 2High Voltage (HV) side and Low Voltage (LV) side respectively✓
- 3High Voltage (HV) side for both tests
- 4Low Voltage (LV) side for both tests
Correct answer
High Voltage (HV) side and Low Voltage (LV) side respectively
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Physics?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Electrical Machines?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Physics · Electrical Machines