During the earthwork planning for a rail line or highway construction in an undulating terrain, which situation should ideally be achieved to minimize the construction cost?
- 1Construction cost is independent of the quantity of cut and fill
- 2Quantity of cut = Quantity of fill✓
- 3Quantity of cut > Quantity of fill
- 4Quantity of cut < Quantity of fill
Correct answer
Quantity of cut = Quantity of fill
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Computer?
Practice full-length Computer mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Transportation Engineering?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Computer · Transportation Engineering