During the change control process, which of the following statements are correct? (i) While a Software Configuration Item (SCI) is under development, it can change freely since it is not under SCM control. (ii) While under review, the SCI is considered to be 'Frozen'. (iii) Once an SCI is reviewed and approved, it is entered into a baseline library under formal SCM control. (iv) Check-in/check-out process: once a change is approved, the SCI is checked out from the library for modification, and then checked back in.
- 1(i), (ii) and (iii)
- 2(ii), (iii) and (iv)✓
- 3(i) and (iv)
- 4(i), (ii), (iii) and (iv)
Correct answer
(ii), (iii) and (iv)
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Computer Science?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Software Engineering?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Computer Science · Software Engineering