Computer · Concrete Technology
Due to a rise in temperature, which of the following changes is expected to occur in fresh concrete?
- 1Bleeding will occur in concrete
- 2Concrete setting time will decrease✓
- 3Concrete shrinkage will increase
- 4The colour of cement concrete will change
Correct answer
Concrete setting time will decrease