Accounting · Labour Efficiency Variance
CT Co. has found that it has had an increasing adverse labour efficiency variance for the last 6 months due to using many temporary workers to meet sales demand. Which TWO of the following control actions could CT Co. implement to try to eliminate this?
- 1Decrease the standard time allowed per unit of product
- 2Reduce the number of supervisors overseeing production
- 3Offer overtime pay to existing skilled employees on a piecework basis and implement training for temporary employees✓
- 4Increase the hourly rate paid to temporary workers
Correct answer
Offer overtime pay to existing skilled employees on a piecework basis and implement training for temporary employees
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Accounting?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Labour Efficiency Variance?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Accounting · Labour Efficiency Variance