Mathematics · Operations Research & Network Analysis
Critical Path Method (CPM) as a project and time management technique:
- 1Estimates optimistic time and pessimistic time
- 2Estimates crash time and normal time✓
- 3Incorporates probabilistic statistical analysis
- 4Uses a multiple time estimate approach
Correct answer
Estimates crash time and normal time