Industrial Engineering · CPM and PERT
Crash cost in project management is associated with:
- 1queueing theory and simulation tech niques
- 2complete revision of project schedule after completion without revised information
- 3allocation of resources and inventory control
- 4an activity when it is completed in the minimum possible time, which is lesser than the expected or normal time✓
Correct answer
an activity when it is completed in the minimum possible time, which is lesser than the expected or normal time
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Industrial Engineering?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on CPM and PERT?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Industrial Engineering · CPM and PERT