Economics · Contract Costing
Cost-plus (cost-sum) contracts are generally executed in which of the following circumstances?
- 1Where the contract must be completed within 24 hours
- 2Where the contractor refuses to accept any profit percentage
- 3Where total costs can be estimated with absolute certainty before commencement
- 4Where it is not possible to estimate the exact total cost and profit in advance due to non-standard work✓
Correct answer
Where it is not possible to estimate the exact total cost and profit in advance due to non-standard work
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Economics?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Contract Costing?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Economics · Contract Costing