Consider the project network given below: Activity A: duration = 14, Predecessors = None Activity B: duration = 13, Predecessors = A Activity C: duration = 20, Predecessors = A Activity D: duration = 10, Predecessors = B, C What is the total project completion time (duration of the critical path)?
- 144✓
- 237
- 327
- 420
Correct answer
44