Computer Science · Operating Systems
Consider the following table about processes, their burst time and arrival time: ProcessBurst TimeArrival TimeP190P2300P340P482P5116 Which of the processes shall finish second to last as per the respective GANTT charts for the non-preemptive SJF and Round Robin (time quantum = 10) scheduling methods?
- 1SJF: P4; RR: P4
- 2SJF: P5; RR: P4
- 3SJF: P4; RR: P3
- 4SJF: P5; RR: P5✓
Correct answer
SJF: P5; RR: P5