Consider the following surveys performed for a engineering project: (i) Reconnaissance survey (ii) Preliminary survey (iii) Traffic survey (iv) Location survey The correct sequence of these surveys conducted to finalize a railway alignment is:
- 1(iii), (i), (ii), (iv)✓
- 2(iii), (i), (iv), (ii)
- 3(i), (iii), (iv), (ii)
- 4(i), (iii), (ii), (iv)
Correct answer
(iii), (i), (ii), (iv)