Consider the following statements regarding resource management in PERT-CPM: Statement I: Resource levelling is a technique where the project duration is kept constant while trying to resolve resource conflicts by utilizing available slack. Statement II: Resource smoothing adjusts activity timings to match resource constraints, often leading to an extension of the original project duration. In light of these statements, which of the following is correct?
- 1Statement I is incorrect but Statement II is correct.
- 2Statement I is correct but Statement II is incorrect.
- 3Both Statement I and Statement II are correct.
- 4Both Statement I and Statement II are incorrect.✓
Correct answer
Both Statement I and Statement II are incorrect.
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for General Studies?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Project Management?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in General Studies · Project Management