Consider the following statements regarding project management: Statement (I): The critical path is defined as the longest duration path between the first and the last nodes of a project. Statement (II): The duration of a project is not always the same as the duration of its critical path. Statement (III): The earliest start and finish times of an activity are based on the condition that every activity will not be started and finished as early as possible. Which of the following options is correct?
- 1Statement (II) is correct, but (I) and (III) are incorrect.
- 2Statement (I) is correct, but (II) and (III) are incorrect.✓
- 3Statements (I) and (III) are correct, but (II) is incorrect.
- 4Statements (I) and (II) are correct, but (III) is incorrect.
Correct answer
Statement (I) is correct, but (II) and (III) are incorrect.
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Current Affairs?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Project Management?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Current Affairs · Project Management