Physics · Project Management
Consider the following statements regarding project management: 1. PERT is probabilistic and CPM is deterministic. 2. In PERT, network slack on various events is calculated, whereas in CPM, floats are calculated. 3. In PERT, activity duration is normally distributed and project duration is beta distributed. 4. The critical path of a network is the path that takes the shortest time. Which of the given statements are INCORRECT?
- 12 and 3
- 23 and 4✓
- 31, 3 and 4
- 41 and 2
Correct answer
3 and 4
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Physics?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Project Management?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Physics · Project Management