Consider the following statements regarding PERT/CPM: Statement 1: The critical path in PERT represents the shortest path in a project network. Statement 2: Activities on the critical path have zero slack time. Which of the statements given above is/are correct?
- 1Both Statement 1 and Statement 2 are correct
- 2Statement 1 is incorrect, but Statement 2 is correct✓
- 3Both Statement 1 and Statement 2 are incorrect
- 4Statement 1 is correct, but Statement 2 is incorrect
Correct answer
Statement 1 is incorrect, but Statement 2 is correct
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for General Studies?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Project Management?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in General Studies · Project Management