Consider the following statements regarding PERT and CPM: 1. PERT is event-oriented while CPM is activity-oriented. 2. PERT is probabilistic while CPM is deterministic. 3. Levelling and smoothing are techniques related to resource scheduling in CPM. Which of the statements given above are correct?
- 11, 2 and 3✓
- 21 and 2 only
- 32 and 3 only
- 41 and 3 only
Correct answer
1, 2 and 3