Consider the following statements regarding network analysis techniques: 1. CPM (Critical Path Method) is an activity-oriented network. 2. PERT (Program Evaluation and Review Technique) is an activity-oriented network. Which of the statements given above is/are true?
- 1Both are true
- 2Both are false
- 3Only 2 is true
- 4Only 1 is true✓
Correct answer
Only 1 is true