Consider the following operations involved in the preparation of brick earth: 1. Digging 2. Weathering 3. Tempering 4. Blending 5. Unsoiling What is the correct chronological sequence of these operations?
- 15, 1, 4, 2, 3
- 25, 1, 2, 4, 3✓
- 31, 5, 2, 4, 3
- 45, 1, 3, 2, 4
Correct answer
5, 1, 2, 4, 3