Consider the expressions for total float in project management: (a) latest start time - earliest start time (b) latest finish time - earliest finish time
- 1Both (a) and (b) are false
- 2(a) is true but (b) is false
- 3Both (a) and (b) are true✓
- 4(a) is false but (b) is true
Correct answer
Both (a) and (b) are true