Mathematics · Project Management
Consider a project with the following activities, precedence, and durations: - P (None, 3 days), Q (None, 4 days) - R (Predecessor: P, 5 days), S (Predecessor: Q, 5 days) - T (Predecessors: R, S, 7 days), U (Predecessors: R, S, 5 days) - V (Predecessor: T, 2 days), W (Predecessor: U, 10 days) Find the critical path of the project.
- 1Q-S-U-W✓
- 2Q-S-T-U
- 3P-R-T-U
- 4P-R-U-V
Correct answer
Q-S-U-W