Mathematics · Estimation and Costing
Compute the total concreting quantity required for a combined footing with two columns of size 400 mm × 400 mm. The dimensions of the combined footing are 3.6 m × 2 m and depth is 440 mm. The height of the column concreting done along with the footing is 1 m above the depth of the footing.
- 15.428 cubic meters
- 24.168 cubic meters
- 34.528 cubic meters
- 43.488 cubic meters✓
Correct answer
3.488 cubic meters
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Mathematics?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Estimation and Costing?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Mathematics · Estimation and Costing