Economics · Capital Budgeting
Company B is faced with two mutually exclusive projects, Project X and Project Y. Both projects have positive NPVs, but Project X has a higher NPV than Project Y. However, Project Y's Internal Rate of Return (IRR) is significantly higher than that of Project X. What is the theoretically correct decision, and what is the reason?
- 1Accept Project Y because the IRR is a direct indicator of project efficiency and return.
- 2Reject both projects until the conflict is resolved, as the IRR and NPV should always rank projects identically.
- 3Accept Project Y because its IRR suggests a quicker payback period, improving short-term liquidity.
- 4Accept Project X, as the objective is to maximise shareholder wealth, and the project with the highest positive NPV achieves this goal.✓
Correct answer
Accept Project X, as the objective is to maximise shareholder wealth, and the project with the highest positive NPV achieves this goal.
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Economics?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Capital Budgeting?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Economics · Capital Budgeting