Mathematics · Estimation and Costing
Calculate the total charges paid to three labourers for excavation work if they work from 9 a.m. to 6 p.m. (including a total of 1 hour of unpaid break, making 8 working hours) with an hourly wage of Rs. 50 per labourer.
- 1Rs. 1,350
- 2Rs. 1,200✓
- 3Rs. 350
- 4Rs. 500
Correct answer
Rs. 1,200