Both PERT and CPM follow a specific sequence of steps in project planning. Identify the correct logical sequence from the options below: 1. Network 2. Identification 3. Time estimates 4. Sequential arrangement 5. Critical path
- 11, 5, 4, 3, 2
- 22, 4, 3, 1, 5✓
- 31, 4, 5, 2, 3
- 42, 3, 4, 1, 5
Correct answer
2, 4, 3, 1, 5