Computer · Irrigation Engineering
Berms are provided in canals when the canal cross-section is:
- 1All of the above
- 2Fully in embankment
- 3Partly in excavation and partly in embankment✓
- 4Fully in excavation
Correct answer
Partly in excavation and partly in embankment