Assertion (A): An Environmental Management Plan (EMP) is ineffective if prepared after project approval. Reason (R): EMP must be integrated during the EIA stage to ensure mitigation measures are embedded in project design. Choose the correct option:
- 1Both A and R are true, and R correctly explains A✓
- 2Both A and R are true, but R does not explain A
- 3A is true, R is false
- 4A is false, R is true
Correct answer
Both A and R are true, and R correctly explains A
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Environment & Ecology?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Environmental Science?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Environment & Ecology · Environmental Science