Assertion (A): Activity-on-Node (AON) diagrams have largely superseded Activity-on-Arc (AOA) diagrams in modern project management. Reason (R): AON networks do not require dummy activities to represent precedence relationships, making them simpler and less error-prone. Which option is correct?
- 1A is false but R is true
- 2Both A and R are true, but R is not the correct explanation of A
- 3Both A and R are true, and R is the correct explanation of A✓
- 4A is true but R is false
Correct answer
Both A and R are true, and R is the correct explanation of A
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for General Studies?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Project Management?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in General Studies · Project Management