Mathematics · Work and Time
Ashok alone can complete a job in 12 days, and Anthony alone can complete it in 15 days. Ashok started the work, worked for 6 days, and then took a break. During the break, Anthony worked on the job. After the break, Ashok returned and both worked together for 2 more days to finish the entire job. How many days was the break (i.e. how many days did Anthony work alone)?
- 12 days
- 26 days
- 35 days
- 43 days✓
Correct answer
3 days