As per the provisions of IS 3370, cracking of concrete in water storage structures can be controlled to some extent by maintaining a maximum rate of filling of ______ at the first time of filling.
- 12 m in 48 hours
- 22 m in 24 hours
- 31 m in 48 hours
- 41 m in 24 hours✓
Correct answer
1 m in 24 hours