Mathematics · Aptitude - CPM Calculation
As per the Critical Path Method (CPM), the earliest start time for an event I is 10 weeks. Activity I-J takes 4 weeks for completion, and the latest occurrence time for event J is 20 weeks. What is the total float for activity I-J?
- 12 weeks
- 26 weeks✓
- 312 weeks
- 416 weeks
Correct answer
6 weeks