Computer · Concrete Technology
As per IS 456, the minimum stripping time required for the soffit formwork to slabs (where props are to be refixed immediately after removal of formwork) is:
- 13 days✓
- 27 days
- 314 days
- 416 to 24 hours
Correct answer
3 days