Computer · Concrete Technology
As per IS 456, for a concrete work quantity of 16 to 30 m3, what is the minimum number of samples required to be taken for testing?
- 14
- 23✓
- 32
- 41
Correct answer
3
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Computer?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Concrete Technology?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Computer · Concrete Technology