As per IS 10262 : 2019, what is the assumed value of standard deviation (S) for M55 grade of concrete?
- 14 N/mm 2
- 23 N/mm 2
- 32 N/mm 2
- 45 N/mm 2✓
Correct answer
5 N/mm 2