Arun and Manish can complete a task in 15 days. Manish and Tarun can complete the same task in 12 days, and Tarun and Arun can complete it in 10 days. Find the time taken by Arun alone to complete the same task.
- 122 days
- 224 days✓
- 318 days
- 425 days
Correct answer
24 days